Facts and figures
Project name: Belwind
Location: 46 kilometre off the coast of Zeebrugge, on the Bligh Bank. It is outside any shipping lanes and outside the 12 mile one. This means Belwind is in international waters in the Belgian Economic Zone (BEZ), in a dedicated zone for the development of wind farms.
Capacity: 165 MW (55 wind turbines of 3 MW)
Foundation:
Type: steel monopile/transition piece
Supplier: Van Oord via EEW (Germany) / Bladt (Denmark)
Design: Van Oord via Ramboll
Installer: Van Oord via Ballast Nedam (the Netherlands)
Diameter: 5 m
Weight monopile: 300 – 550 t
Length monopile: 50 – 72 m
Weight of the transition piece: 120 t
Length of the transition piece: 25 m, 17 m above sea level
Turbines:
Type: V90-3 MW-Offshore
Supplier: Vestas (Denmark - Belgium)
Installer: Vestas
Distance between the turbines: 500 m – 650 m
Rotor diameter: 90 m
Swept rotor area: 6,400 m²
Hub height: 72 m above sea level
Offshore High Voltage Station:
Supplier: THV Seawind & THV BOSS (Belgium)
Weight: 1,100 tonnes
Make topside: Fabricom GDF Suez & Iemants Staalbouw (Belgium)
Number of decks: 5 levels van 375 m²
Make of Main Transformer: CG Holdings (ex-Pauwels Trafo) (Belgium)
Delivery HV Equipment (Siemens): CG holdings
Size of Main transformer: 185 MVA c/w OLTC
Rating of Main Transformer: 200 MVA, 33kV / 150kV (+/- 1.7 %)
Weight of Main Transformer: 151.5 tonnes
Onshore High Voltage Station:
Make: Fabricom GDF Suez (Belgium)
Make Booster Transformer: CG Holdings (Belgium)
Weight of Booster Transformer: 135 tonnes
Rating of Booster Transformer: 185 MVA, 150 kV
Delivery HV Equipment (ABB): CG Holdings (Belgium)
Export cables:
Length of land cable: 3 km
Make of land cable: NKT
Installation of land cable: THV Seawind (Belgium)
Land cable rating: 3 x 1 x 1200 AL, 87/150 kV
Length of sea cable: 52 km
Supplier: Nexans
Installation: Nexans
Cable rating: 3 x 1 x 630/500 mm2 CU, 170 kV
Infield cables: infra-turbine cables
Length: 55 individual lengths of 33 kV-cables (total 50 km)
Supplier: Parker Scanrope
Installation: Van Oord Dredging & Marine Contractors
Sea depth: 15 to 37 metres
Distance from shore: 46 km-52 km
Wind farm area: Phase I: 17 km², phase II: 18 km2
Owner: Belwind NV
Financiers: A consortium of Banks, managed by Dexia (senior) and Rabo Bank (mezzanine), and consisting of EIB, EKF, ASN, Dexia, Rabo.
Contractors:
- Van Oord Dredging & Marine Contractors: design, supply and installation of foundations, off and onshore high-voltage station and cable network, marine operations.
- Vestas: design, supply and installation of turbines, marine operations
Insurance: Portfolio developed by Profin adviseurs & Marsh, insured by Delta Lloyd.
Production: 0.55 TWh a year (phase I), 1.05 TWh for phases I & II
Saved CO2 emissions: 270,000 tonnes of CO2 a year (phase I) and 540,000 tonnes (phase I & II)
Equivalent to: 175,000 households (phase I) and 350,000 households (phase I & II)
Lifetime: Belwind is seeking to generate a maximum amount of wind energy during a period of 20 years and feed this into the Belgian onshore power grid. A maximum extension by (only) 10 years is possible.
Investment: EUR 614 million (phase I)
Unique aspects of the project: In 2009, Belwind is the furthest located offshore wind farm (46 km) in the deepest water (up to 37 m). It was developed in just 3.5 years and built in 15 months. It is also the largest wind farm to be financed on a non-recourse basis.
