In August 2010 all wind turbines will be ready. The offshore high-voltage station will be towed to its location in the wind farm and installed there. The onshore network, including the booster-transformer high-voltage station, will also be ready by then. In September, all the cables are connected and tested. Between October and December the farm will be in a test phase. Towards the end of December the whole park will be operational.
|
April 2006
|
Concession application
|
|
1 July 2006
|
Exclusivity Belwind
|
|
June 2007
|
Concession obtained
|
|
July 2007
|
Submission of Environmental impact evaluation and Sea cable and wind farm permit application. Environmental impact evaluation.
|
|
Sept - Oct 2007
|
Public consultation
|
|
20 February 2008
|
Permit and authorisation for the construction and operation of an offshore wind farm
|
|
12 November 2008
|
Road permit for the land cable and Declaration of Public Interest
|
|
January 2009
|
Flemish building permit for the land cable
|
|
February 2008
|
Permit for the sea cable
|
|
24 July 2009
|
Financial Close
|
|
August 2009
8 september 2009
|
Start of construction: preparatory activities
Installation of the first foundation
|
|
September - February 2010
|
Installation of foundations
|
|
October – March 2010
- August – September 2010
|
Installation transition pieces
Export cable
|
|
August 2010
|
Installation Offshore High Voltage Station (OHVS)
|
|
August 2010
|
Completion Booster transformator station
|
|
March - September 2010
|
Installation turbines
|
|
22 october 2010
|
First delivery of electricity
|
|
31 december 2010
|
Wind farm fully operational
|
|